China China · 25.440, 119.443

Fuqing

Fuqing, nuclear power plant in China, operates 6 pressurized water reactors with 6,150 MW net installed capacity and has been in service since 2014.

Its 6,150 MW net are enough to supply about 19,400,000 households.

Country
China
Units
6
Technology
PWR
Net capacity
6,150 MWe
First grid connection
2014
Operator
Fujian Fuqing Nuclear Power
Owner
China National Nuclear Power Co Ltd
Status
Operating
Operating capacity
6,150 MWe
net electrical
Units
6
6 operating
First start-up
2014

Units

UnitTypeModelStatusMWeMWtConstruction startGrid connectionClosureLoad factor
Fuqing 1Pressurized water (PWR)CNP-1000 (CNNC) (CNP-1000)Operating1,0002,905Nov 21, 2008Aug 20, 2014—84.9 % (2024)
Fuqing 2Pressurized water (PWR)CNP-1000 (CNNC) (CNP-1000)Operating1,0002,905Jun 17, 2009Aug 6, 2015—87.2 % (2024)
Fuqing 3Pressurized water (PWR)CNP-1000 (CNNC) (CNP-1000)Operating1,0002,905Dec 31, 2010Sep 7, 2016—88.6 % (2024)
Fuqing 4Pressurized water (PWR)CNP-1000 (CNNC) (CNP-1000)Operating1,0002,905Nov 17, 2012Jul 29, 2017—33.0 % (2024)
Fuqing 5Pressurized water (PWR)Hualong One (HPR1000)Operating1,0753,050May 7, 2015Nov 27, 2020—87.9 % (2024)
Fuqing 6Pressurized water (PWR)Hualong One (HPR1000)Operating1,0753,060Dec 22, 2015Jan 1, 2022—89.1 % (2024)

Data: IAEA PRIS · Wikipedia · updated on Sep 17, 2026

Fuqing 1, a 1,000 MWe PWR (CNP-1000 (CNNC) (CNP-1000)), started construction in 2008, was connected to the grid in 2014 and is still operating, with a 84.9% load factor in 2024.

Fuqing 2, a 1,000 MWe PWR (CNP-1000 (CNNC) (CNP-1000)), started construction in 2009, was connected to the grid in 2015 and is still operating, with a 87.2% load factor in 2024.

Fuqing 3, a 1,000 MWe PWR (CNP-1000 (CNNC) (CNP-1000)), started construction in 2010, was connected to the grid in 2016 and is still operating, with a 88.6% load factor in 2024.

Fuqing 4, a 1,000 MWe PWR (CNP-1000 (CNNC) (CNP-1000)), started construction in 2012, was connected to the grid in 2017 and is still operating, with a 33% load factor in 2024.

Fuqing 5, a 1,075 MWe PWR (Hualong One (HPR1000)), started construction in 2015, was connected to the grid in 2020 and is still operating, with a 87.9% load factor in 2024.

Fuqing 6, a 1,075 MWe PWR (Hualong One (HPR1000)), started construction in 2015, was connected to the grid in 2022 and is still operating, with a 89.1% load factor in 2024.

Operator: Fujian Fuqing Nuclear Power.

Owner: China National Nuclear Power Co Ltd (Fuqing 1, Fuqing 2, Fuqing 3, Fuqing 4, Fuqing 5, Fuqing 6).

More information

Related plants