🇷🇴 Romania · 44.321, 28.060

Cernavodă

4 reactors PHWR, in service since 1996. Today it delivers 1,300 MWe net, enough for about 4,095,000 households.

Operating capacity
1,300 MWe
net electrical
Units
4
2 operating
First start-up
1996
Cernavodă
Photo: Wikimedia Commons · author and license

Units

UnitTypeModelStatusMWeMWtConstruction startGrid connectionClosureLoad factor
Cernavodă 1Pressurized heavy water (PHWR · CANDU)CANDU-6Operating6502,180Mar 31, 1983Jul 11, 199679.7 % (2024)
Cernavodă 2Pressurized heavy water (PHWR · CANDU)CANDU-6Operating6502,180Jul 1, 1983Aug 7, 200796.2 % (2024)
Cernavodă 3Pressurized heavy water (PHWR · CANDU)CANDU-6Planned7202030 (planned)
Cernavodă 4Pressurized heavy water (PHWR · CANDU)CANDU-6Planned7202031 (planned)

Operator: Societatea Nationala Nuclearelectrica SA.

Owner: Ministerul Economiei; Comertului Si Mediului De Afaceri (Cernavodă 1, Cernavodă 2) · EnergoNuclear SA (Cernavodă 3, Cernavodă 4).

More information