Greifswald
Greifswald, nuclear power plant in Germany, operated 5 pressurized water reactors between 1974 and 1990 and is now shut down.
- Country
- Germany
- Units
- 5
- Technology
- PWR
- Net capacity
- —
- First grid connection
- 1974
- Operator
- Energiewerke Nord
- Owner
- Energiewerke Nord GmbH · VEB KKW "Bruno Leuschner"
- Status
- Shut down
See also: alerts for this plant · every plant in Germany · Vendor: Atomenergoexport (USSR) · every PWR reactor · how a PWR works
Units
| Unit | Type | Model | Status | MWe | MWt | Construction start | Grid connection | Closure | Load factor |
|---|---|---|---|---|---|---|---|---|---|
| Greifswald 1 | Pressurized water (PWR) | VVER-440 (V-230) | Shut down | 408 | 1,375 | Mar 1970 | Dec 1973 | Dec 1990 | — |
| Greifswald 2 | Pressurized water (PWR) | VVER-440 (V-230) | Shut down | 408 | 1,375 | Mar 1970 | Dec 1974 | Feb 1990 | — |
| Greifswald 3 | Pressurized water (PWR) | VVER-440 (V-230) | Shut down | 408 | 1,375 | Apr 1972 | Oct 1977 | Feb 1990 | — |
| Greifswald 4 | Pressurized water (PWR) | VVER-440 (V-230) | Shut down | 408 | 1,375 | Apr 1972 | Sep 1979 | Jun 1990 | — |
| Greifswald 5 | Pressurized water (PWR) | VVER-440 (V-213) | Shut down | 408 | 1,375 | Dec 1976 | Apr 1989 | Nov 1989 | — |
Data: IAEA PRIS · Wikipedia · updated on Sep 17, 2026
Greifswald 1, a 408 MWe PWR (VVER-440 (V-230)), started construction in 1970 and operated from 1973 to 1990.
Greifswald 2, a 408 MWe PWR (VVER-440 (V-230)), started construction in 1970 and operated from 1974 to 1990.
Greifswald 3, a 408 MWe PWR (VVER-440 (V-230)), started construction in 1972 and operated from 1977 to 1990.
Greifswald 4, a 408 MWe PWR (VVER-440 (V-230)), started construction in 1972 and operated from 1979 to 1990.
Greifswald 5, a 408 MWe PWR (VVER-440 (V-213)), started construction in 1976 and operated from 1989 to 1989.
Operator: Energiewerke Nord.
Owner: Energiewerke Nord GmbH (Greifswald 1, Greifswald 2, Greifswald 3, Greifswald 4) · VEB KKW "Bruno Leuschner" (Greifswald 5).