Argentina Argentina · -33.967, -59.209

Atucha

Atucha, nuclear power plant in Argentina, operates one pressurized heavy water reactor with 688 MW net installed capacity and has been in service since 1974. One more unit has its operation suspended.

It is the highest-capacity nuclear plant in Argentina. Unit Atucha 1 has been operating for 52 years, since 1974. CAREM is under construction.

Country
Argentina
Units
4
Technology
PHWR · PWR
Net capacity
688 MWe
First grid connection
1974
Operator
Nucleoelectrica Argentina · Comision Nacional De Energia Atomica
Owner
Nucleoelectrica Argentina SA · China National Nuclear Corp · Comision Nacional De Energia Atomica
Status
Operating
Operating capacity
688 MWe
net electrical
Units
4
1 operating · 1 suspended
First start-up
1974
Atucha
Photo: Wikimedia Commons · author and license

Units

Data: IAEA PRIS · Wikipedia · editorial review · updated on Sep 21, 2026

Atucha 1, a 335 MWe PHWR (Siemens-KWU (PHWR KWU)), started construction in 1968, was connected to the grid in 1974 and is currently suspended.

Atucha 2, a 688 MWe PHWR (Siemens-KWU (PHWR KWU)), started construction in 1981, was connected to the grid in 2014 and is still operating, with a 67.6% load factor in 2024.

Atucha 3, a 1,200 MWe PWR (Hualong One), is planned.

CAREM, a 25 MWe PWR (CAREM Prototyp), has been under construction since 2015.

Operator: Nucleoelectrica Argentina (Atucha 1, Atucha 2, Atucha 3) · Comision Nacional De Energia Atomica (CAREM).

Owner: Nucleoelectrica Argentina SA (Atucha 1, Atucha 2) · China National Nuclear Corp (Atucha 3).