Cogeneration · BWR

BWRX-300

GE-Hitachi's boiling water SMR, derived from the ABWR, under construction at Darlington since 2025.

Natural-circulation boiling-water SMR. ARIS 2024 states 870 MWt and approximately 300 MWe net in its electricity-only configuration; the Canadian licence applies to one specific Darlington unit, not to a universal design certification.

BWR
Technical identity · BWR
Stated output
870 MWt · 300 MWe net · per unit
Maturity
Detailed design
Developer
GE Vernova Hitachi Nuclear Energy
Origin
United States / Japan
01

Energy and applications

Published magnitudes; this is not an engineering diagram.

Thermal output870 MWt
Electrical output300 MWe net
Stated uses
  • Electricity
  • District heating
  • Process heat
02

Three different states

Maturity, licensing and deployment are not equivalent.

01

Maturity

Detailed design

How far the published engineering has progressed.

02

Licensing and review

3 regulatory readings

What a regulator decided, where and on what date.

03

Linked deployment

1 geolocated unit

Which projects or units are linked to the design.

03

Linked deployment

PlantUnitCountryDataset status
Darlington New1Canadaconstruction
04

Licensing and review

What a regulator decided, where and on what date.

JurisdictionReadingMethodDate
Canada · DarlingtonSite construction authorizedPower reactor construction licence for one BWRX-300, valid through 31 March 20352025-04-04
CanadaPre-licensing reviewCombined Phase 1 and 2 vendor design review completed; the CNSC states that this review is not a licence2023-03-15
United StatesPre-licensing reviewNRC pre-application review of topical reports and design white papers2026-09-09
05

Technical sources

How it works and why it matters

The BWRX-300 is a 300 MWe natural-circulation BWR that simplifies the ABWR: no recirculation pumps, isolation valves integrated into the vessel and passive cooling by isolation condensers for seven days. It is the only boiling water SMR under construction.

Ontario Power Generation started building the first unit at Darlington in May 2025, with four planned by 2035. Tennessee Valley Authority, in the United States, and Poland follow.

Quick facts

Power≈ 300 MWe
Typenatural-circulation BWR
ConstructionDarlington, Canada, since May 2025
First operation2029 to 2030