🇫🇷 France · 44.331, 4.731

Tricastin

4 reactors PWR, in service since 1980. Today it delivers 3,660 MWe net, enough for about 11,529,000 households.

Operating capacity
3,660 MWe
net electrical
Units
4
4 operating
First start-up
1980
Tricastin
Photo: Wikimedia Commons · author and license

Units

UnitTypeModelStatusMWeMWtConstruction startGrid connectionClosureLoad factor
Tricastin 1Pressurized water (PWR)CP1Operating9152,785Nov 1, 1974May 31, 198074.4 % (2024)
Tricastin 2Pressurized water (PWR)CP1Operating9152,785Dec 1, 1974Aug 7, 198082.8 % (2024)
Tricastin 3Pressurized water (PWR)CP1Operating9152,785Apr 1, 1975Feb 10, 198167.2 % (2024)
Tricastin 4Pressurized water (PWR)CP1Operating9152,785May 1, 1975Jun 12, 198145.0 % (2024)

Operator: Electricité De France (EDF).

More information