France France · 45.797, 5.271

Bugey

Bugey, nuclear power plant in France, operates 4 pressurized water reactors with 3,580 MW net installed capacity and has been in service since 1972.

Unit Bugey 4 has been operating for 47 years, since 1979. Its 3,580 MW net are enough to supply about 11,300,000 households.

Country
France
Units
5
Technology
GCR · PWR
Net capacity
3,580 MWe
First grid connection
1972
Operator
Electricité de France
Owner
Electricité de France SA
Status
Operating
Operating capacity
3,580 MWe
net electrical
Units
5
4 operating
First start-up
1972
Bugey
Photo: Wikimedia Commons · author and license

Units

UnitTypeModelStatusMWeMWtConstruction startGrid connectionClosureLoad factor
Bugey 1Gas-cooled (GCR / AGR)UNGGShut down5401,954Dec 1965Apr 1972May 27, 1994—
Bugey 2Pressurized water (PWR)CP0Operating9102,785Nov 1, 1972May 10, 1978—89.1 % (2024)
Bugey 3Pressurized water (PWR)CP0Operating9102,785Sep 1, 1973Sep 21, 1978—28.6 % (2024)
Bugey 4Pressurized water (PWR)CP0Operating8802,785Jun 1, 1974Mar 8, 1979—59.5 % (2024)
Bugey 5Pressurized water (PWR)CP0Operating8802,785Jul 1, 1974Jul 31, 1979—57.9 % (2024)

Data: IAEA PRIS · Wikipedia · updated on Sep 17, 2026

Bugey 1, a 540 MWe GCR (UNGG), started construction in 1965 and operated from 1972 to 1994.

Bugey 2, a 910 MWe PWR (CP0), started construction in 1972, was connected to the grid in 1978 and is still operating, with a 89.1% load factor in 2024.

Bugey 3, a 910 MWe PWR (CP0), started construction in 1973, was connected to the grid in 1978 and is still operating, with a 28.6% load factor in 2024.

Bugey 4, an 880 MWe PWR (CP0), started construction in 1974, was connected to the grid in 1979 and is still operating, with a 59.5% load factor in 2024.

Bugey 5, an 880 MWe PWR (CP0), started construction in 1974, was connected to the grid in 1979 and is still operating, with a 57.9% load factor in 2024.

Operator: Electricité de France.

Owner: Electricité de France SA (Bugey 1, Bugey 2, Bugey 3, Bugey 4, Bugey 5).

More information