China China · 22.752, 115.810

Lufeng

Lufeng, nuclear power plant under construction in China, will add 4 pressurized water reactors with 4,732 MW net projected capacity.

Lufeng 1 is under construction.

Country
China
Units
4
Technology
PWR
Net capacity
—
First grid connection
2028
Operator
CGN Lufeng Nuclear Power
Owner
China General Nuclear Power Co Ltd
Status
Under construction
Operating capacity
0 MWe
net electrical
Units
4
0 operating
First start-up
2028

Units

UnitTypeModelStatusMWeMWtConstruction startGrid connectionClosureLoad factor
Lufeng 1Pressurized water (PWR)CAP1000Under construction1,2503,400Feb 24, 2025———
Lufeng 2Pressurized water (PWR)CAP1000Under construction1,2503,400Dec 2025———
Lufeng 5Pressurized water (PWR)Hualong One (HPR1000)Under construction1,1163,180Sep 20222028 (planned)——
Lufeng 6Pressurized water (PWR)Hualong One (HPR1000)Under construction1,1163,180Aug 2023———

Data: IAEA PRIS · Wikipedia · editorial review · updated on Sep 21, 2026

Lufeng 1, a 1,250 MWe PWR (CAP1000), has been under construction since 2025.

Lufeng 2, a 1,250 MWe PWR (CAP1000), has been under construction since 2025.

Lufeng 5, a 1,116 MWe PWR (Hualong One (HPR1000)), has been under construction since 2022, with grid connection expected in 2028.

Lufeng 6, a 1,116 MWe PWR (Hualong One (HPR1000)), has been under construction since 2023.

Operator: CGN Lufeng Nuclear Power.

Owner: China General Nuclear Power Co Ltd (Lufeng 1, Lufeng 2, Lufeng 5, Lufeng 6).