Canada Canada · 45.069, -66.454

Point Lepreau

Point Lepreau, nuclear power plant in Canada, operates one pressurized heavy water reactor with 660 MW net installed capacity and has been in service since 1983.

Unit Point Lepreau 1 has been operating for 43 years, since 1983. Its 660 MW net are enough to supply about 2,080,000 households.

Country
Canada
Units
2
Technology
PHWR · SMR
Net capacity
660 MWe
First grid connection
1983
Operator
New Brunswick Electric Power Commission
Owner
New Brunswick Electric Power Commission · NB Power
Status
Operating
Operating capacity
660 MWe
net electrical
Units
2
1 operating
First start-up
1983
Point Lepreau
Photo: Wikimedia Commons · author and license

Units

UnitTypeModelStatusMWeMWtConstruction startGrid connectionClosureLicence untilLoad factor
Point Lepreau 1Pressurized heavy water (PHWR · CANDU)CANDU 6Operating6602,180May 1, 1975Sep 11, 19822041 (planned)Jun 30, 203230.7 % (2024)
Point Lepreau SMR 1Small modular reactor (SMR)ARC-100Planned100——2029 (planned)———

Data: IAEA PRIS · Global Energy Monitor · Wikipedia · updated on Sep 17, 2026

Point Lepreau 1, a 660 MWe PHWR (CANDU 6), started construction in 1975, was connected to the grid in 1982 and is still operating, with a 30.7% load factor in 2024.

Point Lepreau SMR 1, a 100 MWe gross SMR (ARC-100), is planned, with grid connection expected in 2029.

Operator: New Brunswick Electric Power Commission.