China China · 40.353, 120.549

Xudapu

Xudapu, nuclear power plant under construction in China, will add 4 pressurized water reactors with 4,400 MW net projected capacity.

Xudapu 1-1 is under construction, with grid connection expected in 2028.

Country
China
Units
4
Technology
PWR
Net capacity
—
First grid connection
2027
Operator
CNNC Liaoning Nuclear Power
Owner
China National Nuclear Power Co Ltd
Status
Under construction
Operating capacity
0 MWe
net electrical
Units
4
0 operating
First start-up
2027

Units

Data: IAEA PRIS · Global Energy Monitor · updated on Aug 1, 2026

Xudapu 1-1, a 1,000 MWe PWR (CAP1000), has been under construction since 2023, with grid connection expected in 2028.

Xudapu 1-2, a 1,000 MWe PWR (CAP1000), has been under construction since 2024, with grid connection expected in 2029.

Xudapu 2-3, a 1,200 MWe PWR (VVER-1200 (V-491)), has been under construction since 2021, with grid connection expected in 2027.

Xudapu 2-4, a 1,200 MWe PWR (VVER-1200 (V-491)), has been under construction since 2022, with grid connection expected in 2028.

Operator: CNNC Liaoning Nuclear Power.

Owner: China National Nuclear Power Co Ltd (Xudapu 1-1, Xudapu 1-2, Xudapu 2-3, Xudapu 2-4).