United States United States · 41.243, -88.229

Braidwood

Braidwood, nuclear power plant in United States, operates 2 pressurized water reactors with 2,354 MW net installed capacity and has been in service since 1988.

Unit Braidwood 2 has been operating for 38 years, since 1988. Its 2,354 MW net are enough to supply about 7,420,000 households.

Country
United States
Units
2
Technology
PWR
Net capacity
2,354 MWe
First grid connection
1988
Operator
Exelon Generation
Owner
Exelon Corp
Status
Operating
Operating capacity
2,354 MWe
net electrical
Units
2
2 operating
First start-up
1988
Braidwood
Photo: Wikimedia Commons · author and license

Units

UnitTypeModelStatusMWeMWtConstruction startGrid connectionClosureLicence untilLoad factor
Braidwood 1Pressurized water (PWR)Westinghouse 4-loop (WH 4LP)Operating1,1943,645Aug 1, 1975Jul 12, 1987—Oct 17, 204693.5 % (2024)
Braidwood 2Pressurized water (PWR)Westinghouse 4-loop (WH 4LP)Operating1,1603,645Aug 1, 1975May 25, 1988—Dec 18, 204794.8 % (2024)

Data: IAEA PRIS · Wikipedia · updated on Sep 17, 2026

Braidwood 1, a 1,194 MWe PWR (Westinghouse 4-loop (WH 4LP)), started construction in 1975, was connected to the grid in 1987 and is still operating, with a 93.5% load factor in 2024.

Braidwood 2, a 1,160 MWe PWR (Westinghouse 4-loop (WH 4LP)), started construction in 1975, was connected to the grid in 1988 and is still operating, with a 94.9% load factor in 2024.

Operator: Exelon Generation.

Owner: Exelon Corp (Braidwood 1, Braidwood 2).