🇫🇷 France · 44.143, 4.709

Marcoule

4 reactors — · GCR · FBR, in service since 1956.

Operating capacity
0 MWe
net electrical
Units
4
0 operating
First start-up
1956
Marcoule
Photo: Wikimedia Commons · author and license

Units

UnitTypeModelStatusMWeMWtConstruction startGrid connectionClosureLoad factor
Marcoule G1OtherShut down71956
Marcoule G2Gas-cooled (GCR / AGR)Shut down39260Mar 1955Apr 1959Feb 1980
Marcoule G3Gas-cooled (GCR / AGR)Shut down40260Mar 1956Apr 1960Jun 1984
PhenixFast breeder (FBR)PH-250Shut down130345Nov 1968Dec 1973Feb 2010

Operator: Compagnie Generale Des Matieres Nucleaires (Marcoule G2, Marcoule G3) · Commissariat À L'Energie Atomique [80%]; Electricité De France (EDF) [20%] (Phenix).

Owner: Commissariat À L'Energie Atomique (Marcoule G1, Marcoule G3, Phenix) · Commissariat À L'Energie Atomique [80%]; Electricité De France (EDF) [20%] (Marcoule G2).

More information