United States United States · 37.166, -76.699

Surry

Surry, nuclear power plant in United States, operates 2 pressurized water reactors with 1,676 MW net installed capacity and has been in service since 1972.

Unit Surry 1 has been operating for 54 years, since 1972. Its 1,676 MW net are enough to supply about 5,280,000 households.

Country
United States
Units
2
Technology
PWR
Net capacity
1,676 MWe
First grid connection
1972
Operator
Dominion Energy
Owner
Dominion Resources Inc
Status
Operating
Operating capacity
1,676 MWe
net electrical
Units
2
2 operating
First start-up
1972
Surry
Photo: Wikimedia Commons · author and license

Units

UnitTypeModelStatusMWeMWtConstruction startGrid connectionClosureLicence untilLoad factor
Surry 1Pressurized water (PWR)Westinghouse 3-loop (WH 3LP)Operating8382,587Jun 25, 1968Jul 4, 1972—May 25, 203285.4 % (2024)
Surry 2Pressurized water (PWR)Westinghouse 3-loop (WH 3LP)Operating8382,587Jun 25, 1968Mar 10, 1973—Jan 29, 203390.1 % (2024)

Data: IAEA PRIS · Wikipedia · updated on Sep 17, 2026

Surry 1, an 838 MWe PWR (Westinghouse 3-loop (WH 3LP)), started construction in 1968, was connected to the grid in 1972 and is still operating, with a 85.4% load factor in 2024.

Surry 2, an 838 MWe PWR (Westinghouse 3-loop (WH 3LP)), started construction in 1968, was connected to the grid in 1973 and is still operating, with a 90.1% load factor in 2024.

Operator: Dominion Energy.

Owner: Dominion Resources Inc (Surry 1, Surry 2).

More information