4 reactors LWGR, in service since 1978.
Operating capacity
0 MWe
net electrical
Units
4
0 operating
First start-up
1978

Units
| Unit | Type | Model | Status | MWe | MWt | Construction start | Grid connection | Closure | Load factor |
|---|---|---|---|---|---|---|---|---|---|
| Chernobyl 1 | Graphite-moderated light water (LWGR / RBMK) | RBMK-1000 | Shut down | 740 | 3,200 | Mar 1970 | Sep 1977 | Nov 1996 | — |
| Chernobyl 2 | Graphite-moderated light water (LWGR / RBMK) | RBMK-1000 | Shut down | 925 | 3,200 | Feb 1973 | Dec 1978 | Oct 1991 | — |
| Chernobyl 3 | Graphite-moderated light water (LWGR / RBMK) | RBMK-1000 | Shut down | 925 | 3,200 | Mar 1976 | Dec 1981 | Dec 2000 | — |
| Chernobyl 4 | Graphite-moderated light water (LWGR / RBMK) | RBMK-1000 | Shut down | 925 | 3,200 | Apr 1979 | Dec 1983 | Apr 1986 | — |
Operator: Mintopenergo Of Ukraine.
Owner: SE NNEGC "Energoatom" (Chernobyl 1, Chernobyl 2, Chernobyl 3, Chernobyl 4).