🇹🇷 Türkiye · 36.145, 33.540
Akkuyu
4 reactors PWR, in service since 2023.
Operating capacity
0 MWe
net electrical
Units
4
0 operating
First start-up
2023

Units
| Unit | Type | Model | Status | MWe | MWt | Construction start | Grid connection | Closure | Load factor |
|---|---|---|---|---|---|---|---|---|---|
| Akkuyu 1 | Pressurized water (PWR) | VVER V-509 | Under construction | 1,114 | 3,200 | Apr 2018 | 2023 (planned) | — | — |
| Akkuyu 2 | Pressurized water (PWR) | VVER V-509 | Under construction | 1,114 | 3,200 | Apr 2020 | 2024 (planned) | — | — |
| Akkuyu 3 | Pressurized water (PWR) | VVER V-509 | Under construction | 1,114 | 3,200 | Mar 2021 | 2025 (planned) | — | — |
| Akkuyu 4 | Pressurized water (PWR) | VVER V-509 | Under construction | 1,114 | 3,200 | Jul 2022 | 2026 (planned) | — | — |
Operator: Akkuyu Nuclear JSC.
Owner: Akkuyu Nuclear Joint Stock Company (JSC) (Akkuyu 1, Akkuyu 2, Akkuyu 3, Akkuyu 4).