🇷🇺 Russia · 54.166, 33.236
Smolensk
3 reactors LWGR, in service since 1983. Today it delivers 2,775 MWe net, enough for about 8,741,250 households.
Operating capacity
2,775 MWe
net electrical
Units
3
3 operating
First start-up
1983

Units
| Unit | Type | Model | Status | MWe | MWt | Construction start | Grid connection | Closure | Load factor |
|---|---|---|---|---|---|---|---|---|---|
| Smolensk 1-1 | Graphite-moderated light water (LWGR / RBMK) | RBMK-1000 | Operating | 925 | 3,200 | Oct 1, 1975 | Dec 9, 1982 | — | 79.6 % (2024) |
| Smolensk 1-2 | Graphite-moderated light water (LWGR / RBMK) | RBMK-1000 | Operating | 925 | 3,200 | Jun 1, 1976 | May 31, 1985 | — | 84.6 % (2024) |
| Smolensk 1-3 | Graphite-moderated light water (LWGR / RBMK) | RBMK-1000 | Operating | 925 | 3,200 | May 1, 1984 | Jan 17, 1990 | — | 90.2 % (2024) |
Operator: Rosenergoatom.
Owner: Rosatom (Smolensk 1-1, Smolensk 1-2, Smolensk 1-3).