🇪🇬 Egypt · 31.044, 28.498

El Dabaa

4 reactors PWR, in service since 2028.

Operating capacity
0 MWe
net electrical
Units
4
0 operating
First start-up
2028
El Dabaa
Photo: Wikimedia Commons · author and license

Units

UnitTypeModelStatusMWeMWtConstruction startGrid connectionClosureLoad factor
El Dabaa 1Pressurized water (PWR)VVER-1200/V-529Under construction1,1003,200Jul 20222028 (planned)
El Dabaa 2Pressurized water (PWR)VVER-1200/V-529Under construction1,1003,200Nov 20222029 (planned)
El Dabaa 3Pressurized water (PWR)VVER-1200/V-529Under construction1,1003,200May 3, 20232029 (planned)
El Dabaa 4Pressurized water (PWR)VVER-1200/V-529Under construction1,1003,200Jan 20242029 (planned)

Operator: Nuclear Power Plants Authority.

Owner: Nuclear Power Plants Authority (El Dabaa 4).

More information