Wiki · Accidents

The Chernobyl accident, step by step

At 01:23:40 on 26 April 1986 an operator at Chernobyl 4 pressed the emergency shutdown button. Four seconds later the reactor was destroyed. The shutdown is what destroyed it, and the reason lies in the tips of its own control rods.

RBMK-1000 · Chernobyl 43,200 MWt · no containmentLight roof, no containmentUpper shield2,000 tGraphite1,661 channels24 short rodsfrom below ↑187 rods from aboveCoolant, from belowNew Safe Confinement · 2016One control rodto scale · 7 m of fuel+ reactivity heretop of corebottom of coreBoron carbideabsorberGraphite displacer4,5 mWater below1.25 m · absorbsThermal power01:23:04 to 01:23:47200 MWt3 200 MWt≈ 100 ×AZ-5 · 01:23:40explosionsVoid coefficient after 1986: about +β
  1. 01

    A reactor that gains power when it boils

    Chernobyl 4 was an RBMK-1000: 3,200 thermal megawatts, 1,000 electrical, a graphite core twelve metres across crossed by 1,661 vertical pressure tubes carrying light water that boils inside the channel itself. The graphite moderates; the water only cools. That split of duties defines everything that followed.

    In a PWR or a BWR the water is both moderator and coolant: if bubbles form, there is less moderation, fission falls and power drops by itself. In the RBMK the moderator is solid and stays where it is. Bubbles only remove water, which was also absorbing neutrons, so removing it adds reactivity. That is the positive void coefficient, and in the state the core was in that night it was of the order of +4 β: more steam, more power, more steam.

    On top of that, the reactor had no containment building. It sat in an industrial hall with a light roof, because the worst accident the design contemplated was the rupture of one or two tubes, not of the whole core.

  2. 02

    The test, the xenon and the margin that was spent

    The test itself was reasonable: check that, after a loss of offsite power, the coasting turbogenerator could feed the cooling pumps until the diesels came up. It had been postponed since 1982 and was run at the end of a long day, with the reactor on its way to a scheduled shutdown.

    On 25 April the reactor came down from 3,200 to 1,600 MWt and stayed there for some nine hours at the grid dispatcher's request. At 00:28 on the 26th, during a transfer between regulating systems, power collapsed to about 30 MWt. In a reactor that has been at high power, xenon-135 — a fission product that devours neutrons — builds up exactly when power falls: the reactor poisons itself and will not come back up.

    Getting it to the 200 MWt at which the test was finally run meant pulling rods, and pulling rods, and pulling rods. At 01:22:30 the calculation gave an operating reactivity margin of 8 equivalent rods, against a regulatory minimum of 15. That margin was neither displayed to the operator nor wired into the protection system: it had to be requested. The reactor was left at low power, with xenon in the middle, with almost every rod withdrawn and with very little steam flow: precisely the state in which the void coefficient is most dangerous.

  3. 03

    01:23:04 · the test and the button

    At 01:23:04 the turbogenerator inlet valves closed and the machine began to slow. The main circulation pumps, fed by that same generator, lost flow. Less water through each channel means the water heats up more on its way through, and with the reactor already close to saturation that means more steam.

    More steam, in a reactor with a positive void coefficient, means more power; more power, more steam. Power began to climb slowly. At 01:23:40 the shift chief ordered AZ-5, the emergency shutdown button, which drives every rod into the core at once. It was the correct move: in any other reactor, that is where the story ends.

  4. 04

    The graphite tip · why the shutdown was the trigger

    Of the 211 control rods, 187 entered from above at 0.4 metres per second: eighteen to twenty seconds to cross the seven metres of core. The other 24 are shortened rods that come up from below, and their job is to flatten the power profile in the lower half; the ones that matter here are those from above. Because an RBMK rod was not only absorber: nearly all of them carried a 4.5-metre graphite displacer hanging from the boron carbide, and it was there for neutron economy. With the rod withdrawn, the displacer filled the channel so it would not fill with water, which absorbs neutrons and makes fuel more expensive, and it sat centred in the fuelled region, leaving 1.25 metres of water above it and 1.25 metres of water below.

    There is the mechanism. When the rod starts down, the first thing to enter that bottom metre and a quarter is not the absorber: it is the graphite tip, pushing the water out of that part of the channel. In an instant, at the bottom of the core, an absorber — water — was removed and a moderator — graphite — was put in its place. Local reactivity rises. The rod keeps going down and seconds later the boron shuts that region off, but for those seconds the emergency shutdown begins by adding reactivity instead of removing it. INSAG-7 calls it the positive scram effect, and notes that its magnitude depends on how power is distributed through the core.

    That night it was distributed in the worst possible way. With xenon poisoning the middle and the rods withdrawn, the neutron flux had sunk towards the bottom of the core, exactly where the graphite tips would arrive first. The yardstick for this is β, the fraction of neutrons that come not from fission itself but from the later decay of some fragments, about six thousandths of the total: while reactivity stays under 1 β — one dollar — the chain depends on those late neutrons and the reactor is governed in seconds. Cross the dollar and the chain sustains itself on prompt neutrons alone, and the characteristic time becomes milliseconds.

    The contribution of the graphite tips at the bottom of the core, on top of the steam already forming in the channels with a void coefficient of the order of +4 β, crossed that threshold. From that point no rod travelling at 0.4 metres per second was going to arrive in time: the reactor was no longer governed by mechanisms, it governed itself, by destroying itself.

  5. 05

    01:23:43 · four seconds

    At 01:23:43 the power-excursion signals fired. The records show power passing 530 MWt and still rising; later reconstructions put it at the order of a hundred times rated power before the instruments stopped being of any use. All of it happened in about four seconds.

    Fuel does not melt at that speed: it shatters. Thousands of broken uranium oxide pellets dumped their heat into the channel water at once, the water flashed explosively to steam and the pressure tubes burst. The first explosion, of steam, lifted the 2,000-tonne upper shield. Two or three seconds later came the second, attributed to hydrogen from the zirconium cladding reacting with steam at high temperature.

    With no containment building, that energy took the roof off the hall and left the core open to the air. The graphite burned for ten days and the fire's thermal plume carried fission products kilometres up: some 14 EBq of total radioactivity, 5,200 PBq in iodine-131 equivalent. Two workers died in the explosions and 28 more of acute radiation syndrome in the following weeks, most of them firefighters and plant staff. Pripyat, three kilometres away, was evacuated on the afternoon of the 27th; the 30-kilometre zone, some 116,000 people, during 1986.

  6. 06

    What was changed, and what remains

    The IAEA's first report, INSAG-1 in 1986, put the blame on the operators. In 1992, with the full Soviet data on the table, INSAG-7 corrected it: the operators did break rules, but the accident happened because the reactor could reach a state in which its own emergency shutdown blew it up, and that was in no operating manual.

    The RBMKs that kept running were modified. Enrichment went from 2.0 to 2.4% and later to 2.8% with erbium as a burnable poison; between 80 and 90 fixed absorbers were installed in fuel channels; the minimum rod margin went from 26-30 to 43-48 equivalent rods; the rods were redesigned so that, withdrawn, no water was left beneath the displacer; shutdown time went from 18 to 12 seconds and a fast system of 24 rods was added that inserts at least 2 β of negative reactivity in under 2.5 seconds. The void coefficient ended up of the order of +β.

    Unit 4 was covered by the sarcophagus in November 1986 and since 2016 sits under the New Safe Confinement, a 108-metre-tall steel arch assembled alongside and slid over the building. The other three units kept generating: unit 2 until 1991, unit 1 until 1996 and unit 3 until December 2000. Of the seventeen RBMKs built, seven remain in operation, all in Russia.

Comparison

The three accidents, side by side

Three Mile IslandChernobylFukushima Daiichi
Date28 March 197926 April 198611 March 2011
Reactor906 MWe PWR1,000 MWe RBMK-1000Three BWR Mark I
INES level577
What set it offLoss of feedwater and a relief valve stuck openA low-power test with the rod margin used upEarthquake and tsunami: total loss of electrical power
ContainmentFull; it heldNoneFull; damaged by hydrogen
Fuel45% of the core melted, 62 tCore destroyedThree cores melted
Release≈ 370 PBq, almost all noble gases≈ 14 EBq (5,200 PBq iodine-131 equivalent)570 to 630 PBq iodine-131 equivalent
Deaths from radiationNone2 in the explosions and 28 from acute radiation syndromeNone
EvacuationAdvised for pregnant women and children within 8 kmPripyat and the 30 km zone: about 116,000 people in 1986More than 100,000 people
What changed afterwardsOperator training, control-room interface, INPORods, void coefficient and safety culture across every RBMKBackup power, filtered vents and hydrogen recombiners

Reference

Quick facts

Date26 April 1986 · AZ-5 at 01:23:40
UnitChernobyl 4 · RBMK-1000 · 3,200 MWt · 1,000 MWe
State beforehand≈ 200 MWt · reactivity margin of 8 equivalent rods (minimum 15)
Void coefficientof the order of +4 β in that state
Control rods211 · 187 from above at 0.4 m/s (18 to 20 s) and 24 short ones from below · 4.5 m graphite displacer with 1.25 m of water below
Escalationpower above 530 MWt at 01:23:43 · explosions seconds later
INES level7
Release≈ 14 EBq · 5,200 PBq iodine-131 equivalent
Immediate deaths2 in the explosions · 28 from acute radiation syndrome in the following weeks
EvacuationPripyat on 27 April · 30 km zone, some 116,000 people during 1986
Confinementsarcophagus in November 1986 · New Safe Confinement in 2016
The plant todayunits 2, 1 and 3 shut down in 1991, 1996 and 2000

Further reading

Sources: IAEA INSAG-7, IAEA INSAG-1, World Nuclear Association, UNSCEAR