United States United States · 40.154, -76.725

Three Mile Island

Three Mile Island, nuclear power plant in United States, is preparing the restart of one pressurized water reactor of 835 MW net, not generating since 2019, with a return to service expected in 2027.

Three Mile Island 1's restart is announced for 2027.

Country
United States
Units
3
Technology
PWR
Net capacity
—
First grid connection
1974
Operator
Exelon Generation · General Public Utilities
Owner
Exelon Corp · Constellation Energy Corp
Status
Restarting
Operating capacity
0 MWe
net electrical
Units
3
0 operating
First start-up
1974
Three Mile Island
Photo: Wikimedia Commons · author and license
Official news
  1. NRC
    NRC authorizes receipt of new fuel at the Crane Clean Energy Center

    License Amendment 307 for the former Three Mile Island 1: the plant may receive and store fresh fuel and neutron sources while the restart review continues.

  2. NRC
    Draft environmental assessment: the restart would have no significant impact

    The NRC issued the draft environmental assessment and draft finding of no significant impact, with public comments until July 8. The final version is projected for September 2026.

  3. U.S. Department of Energy
    Department of Energy closes a $1 billion loan for the restart

    The Loan Programs Office finances part of the restoration of the 835 MW unit, which would power the equivalent of about 800,000 homes on the PJM grid.

  4. NRC
    Three Mile Island 1 officially renamed Christopher M. Crane Clean Energy Center

    License Amendment 306: the NRC accepts the facility's new name, in honour of former Exelon CEO Chris Crane.

  5. Constellation
    Constellation ahead of schedule for the restart

    Over 200 employees hired and a new main power transformer ordered for 2026; return to service brought forward to 2027, a year ahead of the original plan.

  6. Constellation
    Constellation announces the restart of Three Mile Island 1 with a 20-year deal with Microsoft

    Five years after the economic shutdown, a power purchase agreement with Microsoft for its data centres funds the return of 835 MW of carbon-free power to the grid.

Units

UnitTypeModelStatusMWeMWtConstruction startGrid connectionClosureLoad factor
Three Mile Island 1Pressurized water (PWR)Babcock & Wilcox lowered-loop (B&W LLP)Restarting · restart expected 20278352,568May 18, 1968Jun 1974Sep 2019—
Three Mile Island 2Pressurized water (PWR)B & W (DRY)Shut down8802,772Nov 1969Apr 1978Mar 1979—
Three Mile Island Unit 1 RepowerPressurized water (PWR)Babcock & Wilcox lowered-loop (B&W LLP)Planned819——2027 (planned)——

Data: IAEA PRIS · Global Energy Monitor · editorial review · updated on Sep 21, 2026

Three Mile Island 1, an 835 MWe PWR (Babcock & Wilcox lowered-loop (B&W LLP)), started construction in 1968 and operated from 1974 to 2019; its restart is expected in 2027 as the Crane Clean Energy Center.

Three Mile Island 2, an 880 MWe PWR (B & W (DRY)), started construction in 1969 and operated from 1978 to 1979.

Three Mile Island Unit 1 Repower, an 819 MWe PWR (Babcock & Wilcox lowered-loop (B&W LLP)), is planned, with grid connection expected in 2027.

Operator: Exelon Generation (Three Mile Island 1) · General Public Utilities (Three Mile Island 2).

Owner: Exelon Corp (Three Mile Island 1) · Constellation Energy Corp (Three Mile Island Unit 1 Repower).