🇨🇳 China · 26.799, 120.152

Xiapu

2 reactors FBR, in service since 2026.

Operating capacity
0 MWe
net electrical
Units
2
0 operating
First start-up
2026

Units

UnitTypeModelStatusMWeMWtConstruction startGrid connectionClosureLoad factor
Xiapu 1Fast breeder (FBR)CFR-600Under construction6421,882Dec 20172028 (planned)
Xiapu 2Fast breeder (FBR)CFR-600Under construction6421,882Dec 20202026 (planned)

Operator: CNNC Xiapu Nuclear Power CO LTD.

Owner: China National Nuclear Power CO LTD [55%]; Fujian Funeng CO LTD [20%]; China Yangtze Power CO LTD [10%]; Huaneng Nuclear Power Development CO LTD [10%]; Ningde State-owned Assets Investment and Operation CO LTD [5%] (Xiapu 1, Xiapu 2).