Nuclear power in Uzbekistan
Uzbekistan has no nuclear reactors operating today. 2 under construction.
Jizzakh will be Uzbekistan's first nuclear power plant, with 2 SMR units and 110 MW net in total; the first grid connection is expected in 2029. Once in service, those 110 MW net would be enough to supply about 347,000 households.
SMR reactors in Uzbekistan · Rankings
Electricity generation mix
Latest year2025
Share of electricity generation, 2025 (closest earlier year; 2026 has no data) · Ember
% of generation
Click a source to show or hide it on the chart
Plants
| Plant | Units | Types | Status today | MWe operating |
|---|---|---|---|---|
| Jizzakh | 2 | SMR | 2 under construction | — |
Data: Global Energy Monitor · Wikipedia · updated on Sep 17, 2026